The original plan, the
plan today
Almost every elementary and middle school in the
City School District of Albany is being newly built and/or
renovated as part of the comprehensive facilities project.
Originally approved by voters in 2001, with referenda to adjust
budgets and the scope of work at particular schools in 2002, the
project has passed its halfway point.
The table below includes
the original budget for each school and how that budget has changed as
the project progressed. The final budgets have been established for the
first four phases. Budgets for the final two phases have not been
established. Schools included in the final two phases are marked with
the notation "TBD".
|
School |
Original
budget (2001) |
Revised budget
(2003) |
Adjustments |
Final budget
(2005) |
| Albany High School |
$527,000 |
$33,000 |
0 |
$560,000 |
| Arbor Hill Elementary
School |
$2,315,000
$6,230,000 |
$15,000
0 |
0
TBD |
$2,330,000
TBD |
Eagle Point Elementary
(formerly PS 27) |
$8,759,000 |
$459,477 |
$842,142 |
$10,491,926 |
| Harriet Gibbons High School |
0 |
$4,020,000 |
0 |
$4,020,000 |
| Giffen Memorial Elementary School |
$9,966,000 |
0 |
TBD |
TBD |
| Hackett Middle School |
$17,450,000 |
0 |
$16,050,000 |
$33,500,000 |
| Philip Livingston Magnet Academy |
$19,422,000 |
0 |
($19,422,000) |
0 |
| Montessori Magnet School |
$9,204,000 |
$577,250 |
0 |
$9,781,250 |
| Stephen & Harriet Myers Middle
School |
$30,914,000 |
$2,843,385 |
0 |
$33,757,385 |
North Albany Academy
(formerly PS 20) |
$9,643,000 |
$506,491 |
$342,435 |
$10,491,926 |
| Thomas O'Brien Academy of Science
& Technology |
$7,420,000 |
0 |
TBD |
TBD |
| Public School 16 |
$10,979,000 |
0 |
$1,721,000 |
$12,700,000 |
| Public School 18 |
$9,907,100 |
0 |
$2,793,000 |
$12,700,000 |
| Public School 19 |
$8,541,000 |
0 |
TBD |
TBD |
Philip Schuyler Achievement
Academy
(formerly PS 21) |
$8,958,000 |
$864,057 |
0 |
$9,822,057 |
| Sheridan Preparatory Academy |
$11,620,000 |
($290,500) |
0 |
$11,329,500 |
| Sunshine Facility |
$1,215,000 |
0 |
($1,184,577) |
$30,423 |
| Land Acquisition |
$3,400,000 |
($258,160) |
|
$3,141,840 |
| |
|
|
|
|
|
TOTAL PROJECT |
$176,470,000 |
$8,770,000 |
|
$185,240,000 |
| |
|
NOTES:
|
| *Philip Livingston
Magnet Academy has been removed from the facilities plan and may
be closed due to projected charter school enrollments. |
| *Sunshine School in
Lincoln Park is no longer used as a school and now serves as
offices for the district's pupil personnel and special education
programs. |
| *The original scope
of work for Arbor Hill Elementary has changed based on
structural problems. |
|
 |
|